*Helped intern Ali with code restructuring
*Finished post-processing TEST SGTs from Titan; close but not identical
*Tried running USC with new hypocenter distributions; error with Pegasus, emailed Gideon
*Queued comparison TEST run on Blue Waters
*SGT generation finished on Titan
*Realized that 1 Hz SGT source was incorrect; generated new sources and resubmitted
*Registered for the Annual Meeting
*Applied for OSG certificate


== Today ==
== Today ==
*Run 1 Hz SGTs on Titan for 4 test sites
*Post-process Titan 1 Hz USC SGTs
*Try latest version of Pegasus, see if it solves the problem
*Queue up PAS, WNGC, SBSM SGTs on Titan
*Respond to Matt about proposal after CyberShake calls
*Get together CyberShake description for ORNL meeting
*Insert uniform hypocenter distribution with ERF 35 into DB


== Blocked ==
== Blocked ==
Line 14: Line 15:


== Follow-ups ==
== Follow-ups ==
*HighF call
*ORNL planning call
*CyberShake calls


== Areas of Responsibilities ==
== Areas of Responsibilities ==

Revision as of 17:04, 17 July 2014

Yesterday

  • Finished post-processing TEST SGTs from Titan; close but not identical
  • Queued comparison TEST run on Blue Waters
  • Realized that 1 Hz SGT source was incorrect; generated new sources and resubmitted
  • Registered for the Annual Meeting
  • Applied for OSG certificate

Today

  • Post-process Titan 1 Hz USC SGTs
  • Queue up PAS, WNGC, SBSM SGTs on Titan
  • Get together CyberShake description for ORNL meeting

Blocked

  • No

Follow-ups

  • ORNL planning call

Areas of Responsibilities

  • CyberShake
  • Broadband CyberShake
  • Code migration