Staff Priorities - Scott: Difference between revisions
From SCECpedia
Jump to navigationJump to search
No edit summary |
No edit summary |
||
| Line 1: | Line 1: | ||
== Yesterday == | == Yesterday == | ||
*Worked on | *Worked on proxy issue - found error with signing policies, still issue in planner | ||
*Checked on monitord population - | *Checked on monitord population for Study 2.2 - almost done | ||
* | *Sent out new SGT metrics | ||
*Still waiting on quota issue... | *Still waiting on quota issue... | ||
*No certs available from TACC or NICS - just proxies | |||
== Today == | == Today == | ||
*Keep working on Pegasus | *Keep working on Pegasus planning issues | ||
* | *Modify workflow generator to support AWP SGTs | ||
== Blocked == | == Blocked == | ||
* | *Waiting on Rob's OK to resample rupture surfaces | ||
== Follow-ups == | == Follow-ups == | ||
Revision as of 17:54, 18 July 2013
Yesterday
- Worked on proxy issue - found error with signing policies, still issue in planner
- Checked on monitord population for Study 2.2 - almost done
- Sent out new SGT metrics
- Still waiting on quota issue...
- No certs available from TACC or NICS - just proxies
Today
- Keep working on Pegasus planning issues
- Modify workflow generator to support AWP SGTs
Blocked
- Waiting on Rob's OK to resample rupture surfaces
Follow-ups
- No
Areas of Responsibilities
- CyberShake 1.4
- Broadband CyberShake
- Code migration