* Fling Study
* Fling Study
** We are now 40/42
** We are now 41/42
** Running 118 and 124 on HPCC, using trunk and updated parallel scripts
** Scenario 124 finished on Saturday, needs to be verified
** Scenario 124 is: 96/178 stations, Scenario 118 is 94/241 stations.
** Running scenario 118 on HPCC, using trunk and updated parallel scripts
** Scenario 118 is 210/241 stations, should finish on Wednesday
** Updated wiki tables: http://scec.usc.edu/scecpedia/Fling_Study#Codebase_URS.2FURS.2FURS.2FURS
** Updated wiki tables: http://scec.usc.edu/scecpedia/Fling_Study#Codebase_URS.2FURS.2FURS.2FURS
* Trac issue #104: Environment variables select GF and validation: almost done
* Fixed Trac issue #77 (UCSB LP validation)
* Met with Phil, discussed design ideas and priorities for Broadband development
* Broadband science call
* Trac issue #104: Environment variables select GF and validation directories: done, testing
* Trac issue #82: Separate validation code from Greens Functions: done, testing
* Trac issue #82: Separate validation code from Greens Functions: done, testing


Line 12: Line 16:


* Fling Study
* Fling Study
** Monitoring running scenarios
** Verify scenario 124, generate tar file, and post data
** Monitoring last running scenario
* Fix issue in GP code where filenames are cut short in site response module
* Trac issue #131: Package new parallel running scripts and check them into svn as part of BBP
* Trac issue #131: Package new parallel running scripts and check them into svn as part of BBP
* Trac #104: Write sample scripts
* Trac #104: Write sample scripts
* Trac #82: Run more acceptance tests  
* Trac #82: Run more acceptance tests
* Fix Trac issue #77 (UCSB LP validation)
* Trac #84: User selectable Greens Functions
* Continue sketching BBP workflow (component by component with input and output files)
* Continue sketching BBP workflow (component by component with input and output files)
* Trac issue #128: Start work on Cruise Control setup
* Trac issue #128: Start work on Cruise Control setup

Revision as of 17:13, 9 July 2012

Yesterday:

  • Fling Study
  • Fixed Trac issue #77 (UCSB LP validation)
  • Met with Phil, discussed design ideas and priorities for Broadband development
  • Broadband science call
  • Trac issue #104: Environment variables select GF and validation directories: done, testing
  • Trac issue #82: Separate validation code from Greens Functions: done, testing

Today:

  • Fling Study
    • Verify scenario 124, generate tar file, and post data
    • Monitoring last running scenario
  • Fix issue in GP code where filenames are cut short in site response module
  • Trac issue #131: Package new parallel running scripts and check them into svn as part of BBP
  • Trac #104: Write sample scripts
  • Trac #82: Run more acceptance tests
  • Trac #84: User selectable Greens Functions
  • Continue sketching BBP workflow (component by component with input and output files)
  • Trac issue #128: Start work on Cruise Control setup

Blocked:

  • No

Followups:

  • No

Ongoing:

  • Look for ways to break up the GF directory layout, some ideas are:
    • Figure out how to separate the validation data from Greens Functions
    • Create separate validation package
    • Separate events from each other