*CyberShake planning call
+
*Monitored Study 15.12, some issues with Pegasus 4.6
*Generated new velocity mesh, with constant mantle velocity and 10 km smoothing
+
*Ran Cori workflow tests, some problems with Pegasus 4.6, worked with ISI
*Pegasus 4.6.0 DB error, nothing can be planned
+
*Generated SRFs for forward test; all the initiation times are 0, checked with Rob, that's not correct
  
 
== Today ==
 
== Today ==
*Resume Study 15.12 once DB issue resolved
+
*Monitor Study 15.12
*Run Cori workflow tests once DB issue resolved
+
*Continue with Cori workflow tests
 
*Install schema and required info on test DB for insertion test
 
*Install schema and required info on test DB for insertion test
*Try to make progress on source conversion for forward test
+
*If Rob gets back to me, integrate changes and recreate SRFs
  
 
== Blocked ==
 
== Blocked ==
Line 14: Line 14:
  
 
== Follow-ups ==
 
== Follow-ups ==
*IHPCSS planning call
+
*No
  
 
== Areas of Responsibilities ==
 
== Areas of Responsibilities ==

Revision as of 18:11, 18 February 2016

Yesterday

  • Monitored Study 15.12, some issues with Pegasus 4.6
  • Ran Cori workflow tests, some problems with Pegasus 4.6, worked with ISI
  • Generated SRFs for forward test; all the initiation times are 0, checked with Rob, that's not correct

Today

  • Monitor Study 15.12
  • Continue with Cori workflow tests
  • Install schema and required info on test DB for insertion test
  • If Rob gets back to me, integrate changes and recreate SRFs

Blocked

  • No

Follow-ups

  • No

Areas of Responsibilities

  • CyberShake
  • Broadband CyberShake
  • Code migration