Difference between revisions of "Product Backlog - William"
From SCECpedia
Jump to navigationJump to search (→Daily) |
|||
Line 3: | Line 3: | ||
== Daily == | == Daily == | ||
* run test case to verify fix of coulomb model [waiting on benchmark from matt] | * run test case to verify fix of coulomb model [waiting on benchmark from matt] | ||
− | * | + | * CSEP1 data modeling |
+ | ** get sqlite tool | ||
+ | ** implement data model | ||
+ | *** build test data | ||
+ | *** import into data base | ||
+ | ** write queries to test | ||
+ | ** expand model to contain csep system | ||
== Project/Product Backlog == | == Project/Product Backlog == |
Revision as of 23:54, 26 March 2018
William Savran's Project/Product Backlog
Daily
- run test case to verify fix of coulomb model [waiting on benchmark from matt]
- CSEP1 data modeling
- get sqlite tool
- implement data model
- build test data
- import into data base
- write queries to test
- expand model to contain csep system
Project/Product Backlog
- implement fixes to CSEP outlined in RFC002
- brainstorm 5 year plans for CSEP2
- investigate parallel reprocessing capabilites of CSEP
- fix SVN issue with localhost path to SVN server on csep-debug
- run forecast for global region on csep-debug to check how year breaks function
- run for 2007
- run for 2018
- create scripts to find forecasts in data archives
- investigate how SVN works with EQ catalogs
- how do we query SVN for previous years using tags
CSEP 5 Year Plan
Immediate
- Fix NZ STEP models. Target date: 1 March 2018.
- Verify CSEP results and data streams. Target date: 15 March 2018.
- Upgrade NZ CSEP version. Target date: 15 March 2018.
- Identify dependencies between NZ forecast groups. Target date: 15 March 2018.
- Identify dependencies between SCEC forecast groups. Target date: 15 March 2018.
Near
- Parallelise reprocessing. Target date: 15 April 2018.
- Complete reprocessing NZ and SCEC. Target date: 15 May 2018.
- Provide access tools to curated CSEP1.0 dataset. Target date: 1 June 2018.
Far
- Prototype (reprocessing) ensemble methods. Target date: 1 July 2018
- Process ensemble models in NZ and SCEC. Target date: 1 August 2018
- Publish results. Target submission date: 1 September 2018.
- Publish results. Target date: 1 November 2018