Difference between revisions of "Staff Priorities - Fabio"

From SCECpedia
Jump to navigationJump to search
Line 1: Line 1:
 
== Yesterday: ==
 
== Yesterday: ==
  
* Created new Trac tickets with issues from BBP meetings from KW, CG, SG
+
* Started work on Trac #146: Remove DT from src file
* Created svn 13.9.0 tag of BBP now that svn/trac issues are resolved
+
** GP method uses 3 separate DT values (RP, LF, HF)
* Cleaned-up old data from broadband-02
+
** Contacted RG to clarify issues, sent him summary
** Restarted broadband.usc.edu server
+
* Talked to JC about UCSB method
** Got epicenter/bbpvault disks remounted
+
** Corner freq is related to source
* Responded to SG regarding using BBP 13.9.0
+
** Update to UCSB method to include hybrid approach: LF/HF
* Updated main wiki page with BBP 13.9.0 link
+
* Supported SG wrt running BBP 13.9.0
  
 
== Today: ==
 
== Today: ==
  
* Prepare for upcoming SWUS runs
+
* Continue work on removing DT from .src file (trac #146)
** KW's new scenarios (TBD)
+
** Add DT to each GF package, remove from SRC file
** KO's re-run requests
+
** Look for DT on UCSB method
* Clean-up data from broadband.usc.edu/rcf-104/epicenter disks
 
* Work on removing DT from .src file (trac #146)
 
  
 
== Blocked: ==
 
== Blocked: ==
Line 21: Line 19:
  
 
== Followups: ==
 
== Followups: ==
* No
+
* Cybershake calls @ 11am
 +
* BBP meeting with PM @ TBD

Revision as of 17:03, 2 October 2013

Yesterday:

  • Started work on Trac #146: Remove DT from src file
    • GP method uses 3 separate DT values (RP, LF, HF)
    • Contacted RG to clarify issues, sent him summary
  • Talked to JC about UCSB method
    • Corner freq is related to source
    • Update to UCSB method to include hybrid approach: LF/HF
  • Supported SG wrt running BBP 13.9.0

Today:

  • Continue work on removing DT from .src file (trac #146)
    • Add DT to each GF package, remove from SRC file
    • Look for DT on UCSB method

Blocked:

  • No

Followups:

  • Cybershake calls @ 11am
  • BBP meeting with PM @ TBD