Line 3: | Line 3: | ||
== Project/Product Backlog == | == Project/Product Backlog == | ||
* build CSEP from source code and create distributable image | * build CSEP from source code and create distributable image | ||
− | + | * run forecast for global region on csep-debug to check how year breaks function | |
− | * run forecast for global region on csep-debug | ||
** run for 2007 | ** run for 2007 | ||
** run for 2018 | ** run for 2018 | ||
Line 10: | Line 9: | ||
* investigate parallel reprocessing capabilites of CSEP | * investigate parallel reprocessing capabilites of CSEP | ||
* write-up batch reprocessing capabilities for Fabio | * write-up batch reprocessing capabilities for Fabio | ||
− | |||
− | |||
* investigate how SVN works with EQ catalogs | * investigate how SVN works with EQ catalogs | ||
− | ** how do we query SVN for previous years | + | ** how do we query SVN for previous years using tags |
== CSEP 5 Year Plan == | == CSEP 5 Year Plan == |
Revision as of 22:30, 9 March 2018
William Savran's Project/Product Backlog
Project/Product Backlog
- build CSEP from source code and create distributable image
- run forecast for global region on csep-debug to check how year breaks function
- run for 2007
- run for 2018
- create scripts to find forecasts in data archives
- investigate parallel reprocessing capabilites of CSEP
- write-up batch reprocessing capabilities for Fabio
- investigate how SVN works with EQ catalogs
- how do we query SVN for previous years using tags
CSEP 5 Year Plan
Immediate
- Fix NZ STEP models. Target date: 1 March 2018.
- Verify CSEP results and data streams. Target date: 15 March 2018.
- Upgrade NZ CSEP version. Target date: 15 March 2018.
- Identify dependencies between NZ forecast groups. Target date: 15 March 2018.
- Identify dependencies between SCEC forecast groups. Target date: 15 March 2018.
Near
- Parallelise reprocessing. Target date: 15 April 2018.
- Complete reprocessing NZ and SCEC. Target date: 15 May 2018.
- Provide access tools to curated CSEP1.0 dataset. Target date: 1 June 2018.
Far
- Prototype (reprocessing) ensemble methods. Target date: 1 July 2018
- Process ensemble models in NZ and SCEC. Target date: 1 August 2018
- Publish results. Target submission date: 1 September 2018.
- Publish results. Target date: 1 November 2018