== Yesterday ==
 
== Yesterday ==
*Tested extract_sgt_mpi with USC - working ok, but want to change wf
+
*Finished on DAX generator modifications
*Worked on DAX generator modifications to use extract_sgt_mpi
+
*Tested TEST site workflow and s351 workflow - validated, better performance!
*Trying out Stampede
+
*Talked with Phil about CyberShake plans
  
 
== Today ==
 
== Today ==
*Continue work on DAX generator modifications
+
*Run s351 workflow without subwf restriction - goal is to roll out into production runs tomorrow
*Test TEST site workflow
+
*Improve parallelization of extract_sgt_mpi
*Watch Morgan's AGU presentation
+
*Adjust striping parameters of extracted SGT files
 +
*If time, continue work on setting up Stampede
  
 
== Blocked ==
 
== Blocked ==
Line 13: Line 14:
  
 
== Follow-ups ==
 
== Follow-ups ==
*No
+
*ALCF call at 2pm PST
 +
*Response to Saba about potential collaboration?
 +
 
  
*Follow-up with Phil next week about CyberShake
+
*Watch Morgan's AGU presentation
 
*Run test of I/O forwarding on Kraken
 
*Run test of I/O forwarding on Kraken
 
*Continue testing compiler optimizations
 
*Continue testing compiler optimizations

Revision as of 18:06, 17 December 2012

Yesterday

  • Finished on DAX generator modifications
  • Tested TEST site workflow and s351 workflow - validated, better performance!
  • Talked with Phil about CyberShake plans

Today

  • Run s351 workflow without subwf restriction - goal is to roll out into production runs tomorrow
  • Improve parallelization of extract_sgt_mpi
  • Adjust striping parameters of extracted SGT files
  • If time, continue work on setting up Stampede

Blocked

  • No

Follow-ups

  • ALCF call at 2pm PST
  • Response to Saba about potential collaboration?


  • Watch Morgan's AGU presentation
  • Run test of I/O forwarding on Kraken
  • Continue testing compiler optimizations
  • Run some I/O tests to get reference values
  • Reply to TACC, NICS regarding authorized people


Areas of Responsibilities

  • CyberShake 1.4
  • Broadband CyberShake
  • Code migration