== Yesterday == | == Yesterday == | ||
− | * | + | * Finalized tests of Anderson GOF |
− | ** | + | ** Code checked into svn |
− | * | + | * Created super tables for events |
− | ** | + | ** Copied data out of HPCC before shutdown |
− | ** | + | * Re-ran Song and SDSU using new GFs |
− | ** | + | ** Same results |
− | * | + | * Created BBP 16.5 RC1 distribution |
− | ** | + | ** GFs and validation packages |
− | * | + | ** Updated wiki |
+ | ** Updated User's Manual | ||
+ | ** Updated Installation Guide | ||
+ | *** Mac OS X page | ||
== Today == | == Today == | ||
− | * | + | * Prepare for code review |
− | ** | + | ** Metric to present |
− | * | + | ** Slides |
− | * | + | * Work on supertable |
− | ** | + | ** Dreger figure 3 code |
− | *** | + | *** Run for each of the 5 methods |
− | + | *** Comparison against matlab code | |
− | * | ||
− | ** | ||
== Blocked: == | == Blocked: == | ||
Line 29: | Line 30: | ||
== Followups: == | == Followups: == | ||
− | * | + | * High-F call @11am |
== To Do: == | == To Do: == |
Revision as of 23:22, 3 May 2016
Contents
Yesterday
- Finalized tests of Anderson GOF
- Code checked into svn
- Created super tables for events
- Copied data out of HPCC before shutdown
- Re-ran Song and SDSU using new GFs
- Same results
- Created BBP 16.5 RC1 distribution
- GFs and validation packages
- Updated wiki
- Updated User's Manual
- Updated Installation Guide
- Mac OS X page
Today
- Prepare for code review
- Metric to present
- Slides
- Work on supertable
- Dreger figure 3 code
- Run for each of the 5 methods
- Comparison against matlab code
- Dreger figure 3 code
Blocked:
- No
Followups:
- High-F call @11am
To Do:
Short Term
Broadband Platform
- Update GP rupture generator - Total: 3 days
- Sent Rob parameters - done
- Integrate code - 1 day
- Run tests for Part-A / Part-B - 2 days
- Anderson GoF code from AS - Total: 3 days
- Analyze code, dependencies, provide AS feedback: 1 day
- Convert code to BBP module, add module to BBP workflow: 1 day
- Test BBP platform, produce new metrics: 1 day
- New BBToolbox version available from SDSU - Total: 3 days
- Incorporate SDSU changes into BBToolbox: 1 day
- Run Part-A/Part-B validations: 2 days
- NGA-West 2 validation on BBP - Total: 6 days
- Contact CG, collect input scenarios: 1 day
- Write test code: 1 day
- Run tests: 2 days
- Review results: 2 days
- Setup laptop as EEW machine in software lab - Total: 1 day
- Erase laptop, install clean Mac OS X, install EEW software: 1 day
- Integrate Rupture Generator code from SG - Total: 28 days
- Review code, understand inputs/outputs, run outside platform: 1 day
- Run Part-A problem using Matlab code, review results: 1 day
- Migrate code into BBP Platform, convert Matlab code into Python/C/Fortran, test: 20 days
- Run Part-A/Part-B validation exercise on HPCC: 5 days (contingent on code performance)
High-F
- Set up High-F code repository - Total: 3 days
- Collect codes from groups, scripts - 1 day
- Select SVN/Github repository - 1 day
- Create repository - 1 day
- Understand how to map station location to grid point - Total: 2 days
- Understand approaches used by AWP and Hercules to map station location to grid point - 1 day
- Discuss with PM, DG, how to use UCVM to do this mapping - 1 day
Medium Term
- Package GF generation code from RG into BBP Platform
- New raytracing code for SDSU method
- Update Anderson method
- Try logging into Gordon