== Yesterday: ==
 
== Yesterday: ==
* Call with Ronnie and Katie about Fling Study
 
** Ronnie will make changes to station lists, then we are good to go
 
* Reproduced Rumi's results using 11.2.3 and her scenarios
 
** Results do not look good when using URS codebase for LF
 
* Initial analysis of space and time requirements for running Fling Study
 
** Short summary: 1.7Tb and about 3 months using only HPCC :-(!
 
 
== Today: ==
 
  
* Organize Fling Study information on the wiki, create progress tables
+
* Organize Fling Study information on the wiki, create progress table
 
** Trac #95 (wiki updating)
 
** Trac #95 (wiki updating)
 
* Test HPCC setup with Fling Study scenario 101 and compare result to Phil's run
 
* Test HPCC setup with Fling Study scenario 101 and compare result to Phil's run
* Meet with Phil and John Yu wrt Fling Study strategy
+
** Results look good
 +
* Ran Fling Study scenario 103 (HPCC)
 +
* Met with Phil and John Yu wrt Fling Study strategy
 +
 
 +
== Today: ==
 +
 
 +
* Validate Fling Study scenario 103
 +
* Continue executing Fling scenarios
 +
* Meet John Yu to coordinate data storage, scenario running
 +
* Create Fling Data repo on scec-00 or scec-01
 +
** Move data from Phil's, John's, and Fabio's directories
 
* Make trunk work both with and without site response
 
* Make trunk work both with and without site response
 +
 +
== Blocked: ==
 +
* No
 +
 +
== Followups: ==
 +
* Meeting with John Yu @ TBD
  
 
== Ongoing: ==  
 
== Ongoing: ==  
Line 19: Line 27:
 
** First candidate is removing the plot directory from the GF directory
 
** First candidate is removing the plot directory from the GF directory
 
** Create separate validation package
 
** Create separate validation package
** Separate events and codebases from each other  
+
** Separate events and codebases from each other
 
 
== Blocked: ==
 
* No
 
 
 
== Followups: ==
 
* Meeting with John Yu and Phil @ TBD
 

Revision as of 17:05, 29 May 2012

Yesterday:

  • Organize Fling Study information on the wiki, create progress table
    • Trac #95 (wiki updating)
  • Test HPCC setup with Fling Study scenario 101 and compare result to Phil's run
    • Results look good
  • Ran Fling Study scenario 103 (HPCC)
  • Met with Phil and John Yu wrt Fling Study strategy

Today:

  • Validate Fling Study scenario 103
  • Continue executing Fling scenarios
  • Meet John Yu to coordinate data storage, scenario running
  • Create Fling Data repo on scec-00 or scec-01
    • Move data from Phil's, John's, and Fabio's directories
  • Make trunk work both with and without site response

Blocked:

  • No

Followups:

  • Meeting with John Yu @ TBD

Ongoing:

  • Look for ways to break up the GF directory layout, some ideas are:
    • First candidate is removing the plot directory from the GF directory
    • Create separate validation package
    • Separate events and codebases from each other