Difference between revisions of "Staff Priorities - Masha"

From SCECpedia
Jump to navigationJump to search
Line 3: Line 3:
 
=== Yesterday ===
 
=== Yesterday ===
  
* CSEP status meeting at 9am
+
* Rescheduled CSEP status meeting for Wednesday, February 27, at 9am
** Posted meeting minutes, sent out next meeting announcement
 
** Email exchange with Danijel to stop STEP Matlab on csep-op
 
  
* csep-op:  
+
* Trac ticket #306 Don't preserve OneDayModelInputCatalog data products within testing framework
** Catching up with one-day Md2 CA forecasts due to the race condition
+
 
 +
* csep-op, csep-cert:  
 +
** Removed STEP Matlab model from CA one-day forecasts groups
  
 
* NZTC:
 
* NZTC:
** Batch processing to generate hybrid forecasts where it left off due to out of disk space (using input catalog up to 2001-2011)
+
** Monitor hybrid forecast generation
 +
** Posted examples of CA alarm-based forecasts per David's request
 +
 
 +
* CSEP new server: ran catalog retrieval tests - much faster than existing VM images
 +
 
 +
* EEW new image: publish directory is not available
  
 
=== Today ===
 
=== Today ===
Line 18: Line 23:
 
* csep-op:  
 
* csep-op:  
 
** Catching up with one-day Md2 CA forecasts due to the race condition
 
** Catching up with one-day Md2 CA forecasts due to the race condition
** Remove STEP Matlab from CA one-day forecasts groups configuration files
+
 
 +
* CSEP new server: run complete set of unit and acceptance tests
  
 
* Trac ticket #306 Don't preserve OneDayModelInputCatalog data products within testing framework
 
* Trac ticket #306 Don't preserve OneDayModelInputCatalog data products within testing framework
  
 
* NZTC: Monitor hybrid forecast generation
 
* NZTC: Monitor hybrid forecast generation
 
* Request from David Rhoades to provide examples of alarm-based forecasts for hybrid forecast
 
  
 
* Open Trac tickets:   
 
* Open Trac tickets:   
Line 35: Line 39:
 
'''Blocked''': None
 
'''Blocked''': None
  
'''Followups''': with Phil on CSEP priorities later this week
+
'''Followups''': with Phil on CSEP priorities at 11:30am
  
 
== Responsiblities ==
 
== Responsiblities ==

Revision as of 18:36, 22 February 2013

Current Activities

Yesterday

  • Rescheduled CSEP status meeting for Wednesday, February 27, at 9am
  • Trac ticket #306 Don't preserve OneDayModelInputCatalog data products within testing framework
  • csep-op, csep-cert:
    • Removed STEP Matlab model from CA one-day forecasts groups
  • NZTC:
    • Monitor hybrid forecast generation
    • Posted examples of CA alarm-based forecasts per David's request
  • CSEP new server: ran catalog retrieval tests - much faster than existing VM images
  • EEW new image: publish directory is not available

Today

CSEP

  • csep-op:
    • Catching up with one-day Md2 CA forecasts due to the race condition
  • CSEP new server: run complete set of unit and acceptance tests
  • Trac ticket #306 Don't preserve OneDayModelInputCatalog data products within testing framework
  • NZTC: Monitor hybrid forecast generation
  • Open Trac tickets:
    • 295 Diagnostics tests should be applied to time-dependent forecasts
    • 303 Process Global experiments for 2012/12: 8-17 due to network issues on csep-op server
    • 302 Develop interactive results viewer application:
      • Waiting for current processing to finish to enable VM

Blocked: None

Followups: with Phil on CSEP priorities at 11:30am

Responsiblities