Staff Priorities - Fabio
From SCECpedia
Jump to navigationJump to searchContents
Yesterday:
- Fling Study
- Monitored Scenario 104 execution
- Moved data from John's Scenario 107
- Updated wiki tables
- Fixed permission issue for Ronnie to update Fling station lists
- Looked at plot directory in GF distribution
Today:
- Fling Study
- Continue to schedule Fling scenarios
- Shepherd Fling scenario 104 (75% done, should finish today)
- Validate John's scenario 107 against mine
- Investigate difference between platform run and Rumi's SDSU's run
- Make trunk work both with and without site response
Blocked:
- No
Followups:
- Talk to Phil about SDSU's validation
- SDSU's result validation with Rumi
Ongoing:
- Look for ways to break up the GF directory layout, some ideas are:
- First candidate is removing the plot directory from the GF directory
- Create separate validation package
- Separate events and codebases from each other