Yesterday

  • Worked on large memory version of SeisPSA
  • Worked with Gideon on getting Condor running on upgraded shock - made progress, but now sched is seg faulting
  • Installed certificates back on shock

Today

  • Continue work on large memory version of SeisPSA
  • Asked John to downgrade to latest stable Condor (8.0.3); test when downgrade complete
  • If Condor up and running, run hazard curve (1 km SGTs, 200m spacing) for Rob

Blocked

  • No

Follow-ups

  • No

Areas of Responsibilities

  • CyberShake 1.4
  • Broadband CyberShake