Broadband Sprints

From SCECpedia
Revision as of 17:50, 24 September 2012 by Maechlin (talk | contribs)
Jump to navigationJump to search

Development targets, Trac Tickets, and other activities related to Broadband Platform development

Sprint 7

  • Spring Dates: 24 Sept - 5 Oct
  1. Integration of the new bbtoolbox model
  2. Modeler access to cluster
  3. Release candidate distribution for v12.10
  4. BBP input to EXSIM input config generator
  5. Install bbp software usable on server and cluster
  6. Data products list generated for validation runs.

Spring 6

  • Spring Dates: 10 Sept - 21 Sept
Sprint Task Estimated LOE Percent Completed
Implementation of the Arias duration GOF plots 3 100
Integration of new bbtoolbox model 5 30
Develop scripts to run bbp on cluster 5 95


Sprint 5

  • Sprint Dates - 27 August - 7 Sept
  1. Calculate velocity profiles (Vp,Vs,rho) for all California validation events
  2. Configure bbp to run on server or cluster
  3. Add Arias duration into validation pipeline
  4. Add Site Correction Module into validation pipeline
  5. End-to-end validation pipeline with both obs and sim processing
  6. Integrate new bbtoolbox codes into pipeline
  7. Configure UCSB and SDSU methods to run LOMAP
  8. Fill out 6 panel bias plots based on 3 methods running on server and cluster
  9. Install bbp software usable on server and cluster
  10. Prepare Broadband 12.8.0 Release, including:
    1. Run full validation tests for three main methods run on both server and cluster.
    2. Produce 12.8.0 distributions of validation and velocity model packages
    3. Update Documentation including Installation and User Guide

Sprint 4

  • Sprint Dates - 13 August - 24 August
  1. Calculate velocity profiles for Landers and Hector Mine station sites
  2. Configure UCSB and SDSU methods to run LOMAP
  3. Post bias plots for LOMAP for 3 main methods on server and on cluster
  4. Add method that raises uncatchable exception to bbp_utils to identify unexpected conditions
  5. Add arias duration into validation pipeline
  6. Add rotd50 into validation pipeline
  7. Check rotd50 results from platform against results from CG
  8. Add site correction module to process observed seismograms
  9. Add observation data processing into validation pipeline
  10. End-to-end validation pipeline with both obs and sim processing.
  11. Data products list generated for validation runs.
  12. Make site response processing optional for validation runs
  13. Update GP codebase with compiler changes
  14. Prepare Broadband 12.8.0 Release
    1. Run full validation tests for three main methods run on both server and cluster.
    2. Produce 12.8.0 distributions of validation and velocity model packages
    3. Update Documentation including Installation and User Guide

Sprint 3

  • Sprint Dates: 30 July - 10 August
  1. Routine plotting of LOMAP full validation with comparison acceleration plots (with fixed label), and Bias GOF plots for LOMA Prieta
  2. LOMAP workflow changed to include rupture generator
  3. Wiki site updated to contain current input files, current GOF, and example comparison plots
  4. URS modules renamed to GP
  5. Documentation on how to setup new GF and validation data
  6. DB code and PEER formatter included in trunk
  7. Rupture generator parameters separated into user selectable (), and modeler adjustable (DLEN, DWID, DT)
  8. ROTD50 running with acceptance test and producing file as part of LOMAP
  9. ARIAS running with acceptance test and producing file as part of LOMAP
  10. Integrate new bbtoolbox into platform

Sprint 2

  • Sprint Dates: 16 July - 27 July
  1. Change validation processing so users specify a velocity model, which then determines the GF used in processing, removing "region" based GF selection in bbp v11.2.3.

Sprint 1

  • Sprint Dates: 2 July - 13 July
  1. Separate Validation Data from BBP software distribution so observational data sets are not distributed as part of BBP software