Staff Priorities - Masha

From SCECpedia
Revision as of 17:42, 20 May 2013 by Liukis (talk | contribs)
Jump to navigationJump to search

Current Activities

Yesterday

  • Sent Tran CSEP status summary since V12.1.0
  • csep-op server:
    •  Reprocessing of updated USGS vs. RELM forecasts for 2008-2012, 2006-2011, 2006-2013 testing periods
    • Data request by David Rhoades (retrospective 10 years of 3-month alarm-based forecasts)
  • Posted CSEP status meeting minutes
  • CSEP Trac tickets:
    • #310 Move the model names from the right-hand-side to the left-hand side of the plot figure for T and W tests
    • #311 Add support for different evaluation tests schedules within the same forecast group
    • #312 Add support for 30-minutes forecasts

Today

CSEP

  • TD: new model installation from MIT
    • Ask John to create TD development image, and login for the modeler
  • csep-op server:
    •  Re-processing to catch up with evaluation during 2 weeks of down time
  • CSEP Trac tickets:
    • #310 Move the model names from the right-hand-side to the left-hand side of the plot figure for T and W tests
    • #311 Add support for different evaluation tests schedules within the same forecast group
    • #312 Add support for 30-minutes forecasts
  • Max Schneider:
    • Discrepancy in logL computations for EEPAS-0S_Combined with start date of 2010/04/01
  • Pending data requests:
    • By Alvaro Gonzalez: to process missed one-day forecasts and latest results

TODO

Blocked: None

Followups: None

Responsiblities